1. Apa yang tetingkap untuk2. WIP: kerja dalam kemajuan menunggu antara operasi3. Tembak di hadapan botol4. Undang-undang Little Cross-Check5. Perubahan masa dan keperluan tambahan6. Rancangan mingguan vs halaman sebenar7. Alasan keterlambatan: satu katalog dan keutamaan8. di telefon9. Boss Dashboard, Pulse dan kerja mingguan10. PermohonanBantuan › Pengeluaran › WIP Rancangan vs Aktual
WIP dan Rancangan vs Aktual - Kerja dalam Kemajuan, Bottlenecks, Overtime dan Rancangan Mingguan vs Aktual
1. Apa yang tetingkap untuk
Beliau menjawab tiga soalan di satu tempat: Berapa banyak yang boleh dilakukan (WIP) sedang menunggu antara operasi dan di hadapan mana kerja mesin sedang mengalir; Kapasiti yang mencukupi minggu ini, masa berlebihan atau pertukaran tambahan diperlukan; berapa banyak rancangan minggu lepas selesai tepat pada masanya dan mengapa pesanan terlambat terlambat. Semua ini berpunca daripada data yang sedia ada: MES peristiwa permulaan/akhir, tarikh permulaan dan selesai operasi, pengesahan, APS Jadual dan kalendar mesin, Stuck Work memegang dan penyelenggaraan pecah.
Tag : WIP dan botol · Perubahan masa dan tambahan · Rancangan mingguan vs real · Penyebab Penundaan. Jendela yang terletak di dalam Pengeluaran Kumpulan daripada Dock.
2. WIP: kerja dalam kemajuan menunggu antara operasi
- Quantity done: for each operation, good + rework quantity in MES finish events; without MES a completed operation counts as the order quantity and the last operation is combined with confirmations. An earlier operation can never appear to have done less than a later one.
- Waiting = quantity done by an operation − quantity done by the next. WIP quantity = done by the first operation − done by the last.
- WIP value = waiting × unit cost × completion ratio. Unit cost comes first from the standard cost (nearest period); completion ratio = material share + labour/overhead share × share of routing time up to that operation. Without a standard the actual cost is used as a full unit and the row is marked with
*(upper bound). - Wait time: time from one operation finishing to the next one starting; if the next has not started the wait is still running (…). Colour: under 1 day green, up to 3 days yellow, above red.
Klik baris perintah membuka Rantaian Operasi: apa yang setiap operasi telah dilakukan dan, pada anak panah antara dua operasi, jumlah tunggu dan masa tunggu. Terbuka dalam pengeluaran menunjukkan pesanan dalam tetingkap Pengeluaran.
3. Tembak di hadapan botol
The work in progress piled up in front of an operation (what the previous operation made and this operation has not processed yet, partial lots included) is that machine's queue; even if the operation has started, the remaining parts are in the queue. The first operation's input is raw material, so it is not counted as queue. Per machine you see the number of queued orders, queue hours (operation time × quantity piled up in front; + setup if the operation has not started), the oldest wait and the queue days (queue minutes ÷ the machine's daily capacity this week, from the APS calendar). The daily capacity of work center boxes is the APS work center capacity (efficiency included). The queue in front of a machine with unknown capacity (an undefined machine) is red because it can never be processed. Queue days under 1 are green, up to 3 yellow, 3 or more red — the worst machine is shown as the bottleneck. Open in APS goes to the Bottleneck tab of the Production Schedule, where the "Add 1 shift" scenario calculates the effect.
4. Undang-undang Little Cross-Check
Perintah yang telah selesai pada akhir 28 hari-hari penghantaran (λ, pesanan/hari) dan masa aliran purata (W, hari dari permulaan operasi pertama - atau tarikh pembukaan pesanan - sehingga pengesahan terakhir) dikira; L = λ × W jumlah pesanan yang dijangka dalam sistem. Jika jumlah pesanan yang dimulakan tetapi tidak selesai sekarang, ia beralih daripada anggaran ini dengan lebih daripada 25% peringatan "aliran tidak seimbang" muncul: di atas WIP adalah mengisi, di bawah bermakna garis kosong. pemeriksaan menggunakan pesanan mengira kerana jumlah produk yang berbeza tidak boleh ditambah.
The verdict depends on the absolute difference. If the difference between observed and estimated is less than 3 work orders, the flow counts as balanced. If it is 3 or more: when the estimate is at least 1 order the percentage deviation must also exceed 25%; when the estimate is under 1 order (a workshop with few orders, or data where confirmations were entered in bulk) the percentage is meaningless and is not shown, but a build-up is still reported with the "not balanced" warning.
5. Perubahan masa dan keperluan tambahan
Rangkaian menunjukkan Pusat Kerja × minggu beban (mesin tanpa pusat kerja mempunyai baris sendiri). Kapasiti berasal daripada APS kalendar mesin (perubahan, pecahan, penyelenggaraan yang dirancang, masa tamat tempoh, hari berlebihan). Perkataan daripada operasi terbuka di pejabat APS jadual; masa yang tersisa operasi terbuka tidak dalam jadual ditambah kepada minggu pelan operasi, pelan pesanan atau tarikh yang dibayar (tarikh lulus pergi ke minggu ini). 85% daripada kuning sehingga 100% merah di atas.
- Overload = load − capacity (member machines of a work center share each other's load).
- OT capacity = crew × weekly overtime cap per person; the cap is read from the active HR regulation (daily × working days, weekly cap, the remaining yearly allowance spread over the remaining weeks — Türkiye 3 h/day and 270 h/year, Indonesia 4 h/day and 18 h/week). Overtime already used this year is read from timekeeping. It is also limited by the machine's free calendar time.
- Extra shifts = ⌈overload ÷ shift length⌉ (shift length from the calendar).
- Suggestion: Overtime is enough · OT not enough: extra shift · OT and extra shifts not enough: subcontract or move load · No capacity: move the load to another machine (machine under maintenance or inactive).
The current week counts from today. This week's capacity and overtime allowance are calculated only from the days between today and the end of the week; capacity of days already past can no longer be used, while overdue load is written into this week. If a row has no capacity at all in the remaining days of the week (for example at the weekend), the load falling into that week is moved to the first week with capacity; if no row has remaining capacity, the Boss Dashboard and the weekly page show the overtime need for next week. The "No capacity" suggestion stays only on a row that has no capacity anywhere in the horizon. A work center row's capacity is the APS work center capacity (efficiency included). The Company reports › Machine utilization and OEE button above the grid opens the actual machine utilization for the same weeks.
6. Rancangan mingguan vs halaman sebenar
- Planned finish, in order: the APS operation plan → the official APS schedule / capacity plan → the order's planned start + planned duration → the due date. The bottom of the page says how many orders came from each source.
- Planned: orders whose planned finish falls in this week (count, quantity, total operation time). Actual: orders completed in the week, confirmed quantity and working hours in the week (MES net run time + confirmation time not linked to MES).
- On time % = completed on or before the planned finish ÷ evaluated (orders whose planned day has not come yet count as "waiting").
- Late: orders planned for this week that finished late or are still open + carried over open orders from earlier weeks; delay days are counted from the planned finish.
- The delay reason Pareto, this week's overtime / extra shift need, the WIP summary and next week's risks (Stuck Work due-date radar) are on the same page.
Print opens the page in A4 layout; the PDF is produced on the server (print from the browser if the message service is off). Numbers are written in the format of the document's language. Save snapshot freezes the week's figures — saving the same week again updates the same record, no new record is created; the version goes up only if the figures changed. Send: an in-app message to the chosen users, an e-mail with the PDF attached to the e-mail addresses, a short summary to the WhatsApp numbers.
Drilling into the company report. The Company reports › Planned and actual production button at the top of the page opens, in the Reports window, the planned / actual comparison of the same week by work order and operation (permission: general reports).
Past weeks. On the page of a past week the WIP and overtime figures are not calculated from today; they are shown only from a snapshot taken during that week (the weekly job takes the new week's snapshot every Monday). If there is no such snapshot these two boxes stay empty and a note appears on the page.
7. Alasan keterlambatan: satu katalog dan keutamaan
Katalog ini mempunyai lapan sebab sistem: kekurangan bahan, kerosakan mesin, kekurangan kakitangan, masalah kualiti, perubahan rancangan, penundaan pembekal, perubahan pelanggan, lain-lain; yang baru boleh ditambah, sebab-sebab sistem tidak pernah dipadamkan (mereka boleh dimatikan, kecuali yang lain). Kod sumber mapping Perbezaan antara kerja-kerja yang bertepatan dengan alasan, MES sebab masa tamat tempoh (atau kategori) dan kod kegagalan penyelenggaraan (atau kategori) untuk katalog ini; kod yang tidak dipaparkan jatuh ke lain.
The reason for a late order is found in this order: correction (a reason overridden manually with plan_gercek_yonet) > manual assignment (an assigned reason comes before all automatic sources) > Stuck Work hold (with a known reason) > MES downtime (a downtime event linked to the order) > maintenance breakdown (a breakdown work order on the order's machine overlapping the order's time) > "unknown" hold (a hold the Stuck Work job opens on its own for late orders, carrying no reason — used only when there is no other evidence, falls to Other). Within a source the longest record wins. If none exists the row shows "No reason assigned" in yellow; choose one with Assign reason. Each assignment deactivates the previous one (nothing is deleted) and stays in the log.
8. di telefon
Pada skrin kecil, tetingkap beralih ke tataletak Taman: Kesimpulan (Pada minggu ini KPI kad, pusat kerja yang paling sibuk, sebab Pareto), Lambat (Penyenaraian kad; menandakan satu membuka seorang ahli sihir tiga langkah: 1 Perintah · 2 sebabnya · 3 Hasilnya) dan WIP (Kartu yang digunakan untuk mesin) Target yang paling kurang 44 daripada pixels.
9. Boss Dashboard, Pulse dan kerja mingguan
- The Boss Dashboard's attention box shows money tied up in WIP and this week's overtime / extra shift need (red if overtime and extra shifts are not enough; at the weekend for next week).
- In the Pulse mobile interface a work center over capacity this week appears as an attention row.
- The weekly job is off by default (
PLAN_GERCEK_GOREV=1). When on, on Monday morning (PLAN_GERCEK_GUN,PLAN_GERCEK_SAAT) it saves the snapshot of last week and of the new week — at most once a day per week, and the version goes up only when the figures change; the new week's record keeps that week's WIP and overtime figures as measured during the week. Once a week it writes an in-app summary message to managers and users withplan_gercek_yonetor production planning permission. E-mail and WhatsApp are not sent by the job; use Send on the page.
10. Permohonan
- View:
plan_gercek,plan_gercek_yonetor one of the production permissions. - Assign a reason to a late order:
plan_gercek(or production planning). - Correct the automatic reason, catalogue, mapping, saving and sending snapshots:
plan_gercek_yonet. - Run the job manually: system administrator. Writing also requires the write gate to be open and the user not to be read-only.